Haringey Civic Centre Redevelopment logoHaringey Civic Centre Redevelopment

Milestones

The project will be delivered in key stages within the Project delivery programme gateway approval process (RIBA Stage 1 for Feasibility, Combined RIBA Stage 2/3 Concept and Detailed Design, RIBA Stage 4 Technical Design and Pre -Tender documentation) to facilitate an anticipated Traditional Procurement adopting a JCT Contract form.
  • Design Team Appointment (RIBA Stages 2-6)

    October 2021

     

    -

     

    January 2022

    Design team appointment
  • Cabinet - Business Case Approval

    January 2022

     

    -

     

    January 2022

    Cabinet
  • RIBA Stage 2 - Concept Design Completion

    January 2022

     

    -

     

    September 2022

    RIBA stage 2
  • Enabling works and strip out contract

    March 2022

     

    -

     

    September 2022

    Strip out - start
  • RIBA Stage 3 (Detailed/ Spatial Design) Completion

    September 2022

     

    -

     

    April 2023

    RIBA stage 3
  • Cabinet - Business Case Update and Approval

    April 2023

     

    -

     

    April 2023

    Cabinet business update
  • Planning and Listed Building Consent Applications Submissions

    April 2023

     

    -

     

    May 2023

    Planning application submission
  • Preparation of Tender Documentation

    May 2023

     

    -

     

    September 2023

    RIBA stage 3 plus and preparation of tender documentation
  • Planning and Listed Building Consent Determination

    September 2023

     

    -

     

    October 2023

    Planning determination
  • Main Contractor Procurement

    December 2023

     

    -

     

    Summer 2024

    Contractor procurement
  • Cabinet Decision – Main Contract Award

    Autumn 2024

     

    -

     

    Autumn 2024

    Construction start
  • Construction - Start on site

    Spring 2025

     

    -

     

    Spring 2025

    Construction start
  • Practical Completion

    Summer 2026

     

    -

     

    Summer 2026

    Practical completion
  • Client Fit Out Completion and Client Occupation

    Summer 2026

     

    -

     

    Autumn 2026

    Client fit out